Air Change Rate Calculator

Room volume to required airflow, or airflow back to the rate it delivers. Runs in your browser — nothing is sent anywhere.

Room volume
144.0 m³
Required airflow
4,320 m³/h
Same figure in CFM
2,543 CFM

This is arithmetic, not a design. The rate a room should run at comes from its calculated load, its contamination generation and the recovery time it has to meet.

The formula

Q = V × ACPH

Airflow equals room volume times air changes per hour. Everything on this page is that identity solved in one direction or the other, with a unit conversion attached.

Typical bands

Grade A / ISO 5 unidirectional
Velocity-driven: 0.36 – 0.54 m/s at the working position
Grade B / ISO 5 – 7
40 – 60 ACPH
Grade C / ISO 7 – 8
20 – 40 ACPH
Grade D / ISO 8
10 – 20 ACPH
Controlled, unclassified
6 – 12 ACPH
Classification reference

Questions

About air change rates

How is air change rate calculated?
Air changes per hour is the supply airflow divided by the room volume: ACPH = Q ÷ V, where Q is in cubic metres per hour and V is the room volume in cubic metres. Rearranged, the airflow a room needs at a target rate is Q = V × ACPH.
Does a higher air change rate always mean a cleaner room?
Only up to a point, and never on its own. Dilution helps, but airflow pattern, filtration, pressure regime and the way people move through the room decide whether contamination reaches product. Raising the rate on a room with a poor airflow pattern raises the energy bill without improving the result.
How do I convert m³/h to CFM?
Multiply cubic metres per hour by 0.5886 to get cubic feet per minute; divide by the same figure to go the other way. The calculator on this page shows both at once.
What rate should my cleanroom be designed to?
The rate that satisfies the room's calculated heat and moisture load, its contamination generation, and the recovery time it must meet after a disturbance. Published bands are useful for checking a number is plausible; they are not a substitute for the calculation, and designing from a table is how rooms end up either failing recovery or costing far more to run than they need to.