Scheduled interval
EU GMP Annex 1 sets a maximum interval of 6 months for Grade A and B, 12 months for Grade C and D.
Technical resources
Five stages, in order, each answering one question. Most explanations restate the acronym; this says what actually changes between them.
EU GMP Annex 15
A stage cannot be run before the one above it. Skipping a prerequisite does not save time — it moves the failure later, where it costs more.
What does this facility have to do?
Nothing yet — it states the requirement everything later is measured against. A qualification program with no URS has no benchmark, and every subsequent stage becomes a matter of opinion.
Needs first: The process, the product and the regulatory market it serves.
Will the design, as drawn, satisfy that requirement?
That the proposed design meets the URS and the applicable regulations — before construction commits the money. Usually supported by a traceability matrix linking each requirement to the drawing, calculation or specification that meets it.
Needs first: An approved URS and a design package to check against it.
Was it installed the way it was specified?
That the equipment on site is the equipment that was specified, installed correctly and completely: right model, right materials, right connections, with drawings, certificates and manuals present and correct. This is where an incomplete equipment file becomes visible.
Needs first: Construction complete and commissioned, with a turnover package.
Does it work across its whole operating range?
That the system operates as intended throughout its range — not merely that it runs. Alarms, interlocks and failure responses are tested at the limits, because a system only ever proves itself at the edges of what it is asked to do.
Needs first: A completed IQ. Testing an installation that was never verified proves nothing.
Does it keep working, under real conditions, over time?
That the system performs reproducibly in the operational state, with people and product present. For a cleanroom that means sustained classification, recovery and pressure performance — held, not achieved once.
Needs first: A completed OQ, and the facility running as it will in production.
After handover
A qualified facility does not stay qualified on its own. These are the four things that require a return to it.
EU GMP Annex 1 sets a maximum interval of 6 months for Grade A and B, 12 months for Grade C and D.
Plant replacement, layout modification, or a change to the control system or its configuration.
Recovery time, pressure differential or particle counts trending away from the qualified baseline.
Any intervention that could affect the validated state, assessed under change control.