DQ, IQ, OQ, PQ — Qualification Reference

Five stages, in order, each answering one question. Most explanations restate the acronym; this says what actually changes between them.

EU GMP Annex 15

What each stage proves

A stage cannot be run before the one above it. Skipping a prerequisite does not save time — it moves the failure later, where it costs more.

  1. URS

    User Requirement Specification

    What does this facility have to do?

    Nothing yet — it states the requirement everything later is measured against. A qualification program with no URS has no benchmark, and every subsequent stage becomes a matter of opinion.

    Needs first: The process, the product and the regulatory market it serves.

    • User Requirement Specification
    • Room classification schedule
    • Critical parameter list
  2. DQ

    Design Qualification

    Will the design, as drawn, satisfy that requirement?

    That the proposed design meets the URS and the applicable regulations — before construction commits the money. Usually supported by a traceability matrix linking each requirement to the drawing, calculation or specification that meets it.

    Needs first: An approved URS and a design package to check against it.

    • DQ protocol and report
    • Requirement traceability matrix
    • Design review records
  3. IQ

    Installation Qualification

    Was it installed the way it was specified?

    That the equipment on site is the equipment that was specified, installed correctly and completely: right model, right materials, right connections, with drawings, certificates and manuals present and correct. This is where an incomplete equipment file becomes visible.

    Needs first: Construction complete and commissioned, with a turnover package.

    • IQ protocol and executed report
    • Equipment file and certificates
    • As-built verification
  4. OQ

    Operational Qualification

    Does it work across its whole operating range?

    That the system operates as intended throughout its range — not merely that it runs. Alarms, interlocks and failure responses are tested at the limits, because a system only ever proves itself at the edges of what it is asked to do.

    Needs first: A completed IQ. Testing an installation that was never verified proves nothing.

    • OQ protocol and executed report
    • Alarm and interlock test records
    • Calibration certificates
  5. PQ

    Performance Qualification

    Does it keep working, under real conditions, over time?

    That the system performs reproducibly in the operational state, with people and product present. For a cleanroom that means sustained classification, recovery and pressure performance — held, not achieved once.

    Needs first: A completed OQ, and the facility running as it will in production.

    • PQ protocol and executed report
    • Classification and recovery results
    • Release for production

After handover

What sends you back to qualification

A qualified facility does not stay qualified on its own. These are the four things that require a return to it.

Scheduled interval

EU GMP Annex 1 sets a maximum interval of 6 months for Grade A and B, 12 months for Grade C and D.

Significant change

Plant replacement, layout modification, or a change to the control system or its configuration.

Sustained performance shift

Recovery time, pressure differential or particle counts trending away from the qualified baseline.

After remedial work

Any intervention that could affect the validated state, assessed under change control.

Questions

About qualification

How we run qualification
What is the difference between OQ and PQ?
OQ proves the system works across its whole operating range, tested at the limits with alarms and interlocks exercised — usually with the facility empty. PQ proves it keeps working under real production conditions, with people and product present, held over time rather than achieved once. A system can pass OQ and fail PQ, which is exactly what PQ exists to catch.
Can qualification start before commissioning is finished?
It should not. Commissioning removes engineering defects; qualification documents compliance. Starting IQ against an open punch list means the qualification protocol becomes a snag list, deviations multiply, and the record ends up documenting the construction rather than the facility.
Is DQ actually necessary?
It is where the money is saved. DQ checks the design against the URS before construction commits to it. Finding that a pressure regime cannot hold, or that a room has no maintenance access, is inexpensive on a drawing and very expensive once the ductwork is in a ceiling.
How often does a qualified facility need requalification?
EU GMP Annex 1 indicates six months for Grade A and B areas and twelve months for Grade C and D, and your own monitoring plan may set shorter intervals. Requalification is also triggered by significant change, by a sustained shift in performance, and after any remedial work assessed as affecting the validated state.
Who writes and approves the protocols?
Protocols are approved by the client's quality unit — that is not delegable. Humiley writes them, executes them jointly with the site's QA and QC teams, and hands over the executed package. The evidence belongs to the facility from the day it is generated.