The critical zone: open product, aseptic connections, filling.
- At rest
- ISO 5
- In operation
- ISO 5
Technical resources
Every ISO 14644-1 class, every particle size, and the GMP grade each one answers to. Reproduced for convenience — the standard itself governs.
ISO 14644-1
Maximum permitted particles per cubic metre, equal to or larger than the stated size. A dash means the standard does not define a limit at that size for that class.
| Class | ≥ 0.1 µm | ≥ 0.2 µm | ≥ 0.3 µm | ≥ 0.5 µm | ≥ 1 µm | ≥ 5 µm |
|---|---|---|---|---|---|---|
| ISO 1 | 10 | — | — | — | — | — |
| ISO 2 | 100 | 24 | 10 | — | — | — |
| ISO 3 | 1,000 | 237 | 102 | 35 | — | — |
| ISO 4 | 10,000 | 2,370 | 1,020 | 352 | 83 | — |
| ISO 5 | 100,000 | 23,700 | 10,200 | 3,520 | 832 | — |
| ISO 6 | 1,000,000 | 237,000 | 102,000 | 35,200 | 8,320 | 293 |
| ISO 7 | — | — | — | 352,000 | 83,200 | 2,930 |
| ISO 8 | — | — | — | 3,520,000 | 832,000 | 29,300 |
| ISO 9 | — | — | — | 35,200,000 | 8,320,000 | 293,000 |
A class is only meaningful with its occupancy state attached. The same room is a different class as-built, at rest and in operation, and a limit quoted without one cannot be verified.
Limits from ISO 14644-1:2015, Table 1. ISO 14644-1 © ISO. Obtain the standard from iso.org or your national standards body.
EU GMP
The particle classification each grade maps to. A grade carries microbiological limits, airflow and gowning requirements as well — design against Annex 1, not against this table.
The critical zone: open product, aseptic connections, filling.
The background environment to a Grade A zone.
Preparation and less critical stages of sterile manufacture.
Support areas: component handling, material entry, technical zones.
Air change rates
Bands, not values. The correct rate for a room comes from its calculated load, contamination generation and required recovery time.
Grade A / ISO 5 unidirectional
Velocity-driven: 0.36 – 0.54 m/s at the working position
Sized on airflow velocity across the zone rather than on room air changes.
Grade B / ISO 5 – 7
40 – 60 ACPH
High turnover to hold classification with personnel present.
Grade C / ISO 7 – 8
20 – 40 ACPH
Typical for preparation and compounding areas.
Grade D / ISO 8
10 – 20 ACPH
Support and material handling areas.
Controlled, unclassified
6 – 12 ACPH
Technical corridors and warehousing.