Write the asset register during the project
Tag numbers, serials, locations, criticality and spares all pass through a project before handover. Name one person to hold the asset register from the design tag list, fill it through procurement and FAT, and check it at the IQ walkdown, so loading the CMMS at handover takes days rather than a months-long survey.