After more than twenty years with automation vendors and running an EU-GMP EPC contractor, Tony Nguyen saw problems start at the handovers between companies rather than inside any one scope. This note explains why Humiley is organized as one accountable team across design, project management, equipment and maintenance.
Duct leakage, cascade balance, controls tuning and recovery can only be measured once an AHU is connected on site. A FAT can still speed up those tests by recording clean filter and coil pressure drops, the casing leakage result, fan airflow at design static and the panel software version with its I/O list.
On multi-contractor sites the decisions between scopes go unowned first: envelope penetrations, punch-list closure, construction cleanliness, interface as-builts and turnover sign-off. A RACI works when it names those decisions, with one accountable person each, and is reviewed whenever a scope changes.
Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.
Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.
Where a SCADA, BMS or EMS records GMP-relevant data, access control, clock synchronization, alarm records and audit trails are decided by the electrical and automation engineers. Many sites keep those parameters on a separate validated EMS. Humiley's cross-functional training covers GMP, validation and project management.
In an FMEA risk register, severity 10, occurrence 2 and detection 3 score an RPN of 60, below a nuisance risk at 100. Add a rule that any severity 9 or 10 comes to the weekly review whatever its RPN, and re-rate every risk after its mitigation.
EU GMP Chapter 4 asks that any alteration is signed and dated, leaves the original readable and records a reason where appropriate. Correction fluid, overwritten digits and blacked-out entries all break that rule and ALCOA+. Engineering and site teams need it in their induction as much as QA.
A weekly FMEA review earns its time only when it ends in decisions. Ask the same five questions every week: what is new, which scores moved and why, who owns each open risk, what the next action is and when, and what can be closed on evidence.
A calibration certificate that expires partway through air balancing leaves the later readings without a traceable instrument at OQ review. Before commissioning, list every instrument that will produce a qualification reading, check each due date against the whole test window plus slippage, and record the serial on every test sheet.
ICH Q9(R1), adopted in January 2023, says the formality of quality risk management should rise with uncertainty, importance and complexity. Write into change control what sends a change to a full FMEA, such as airflow, pressure regime, the critical zone or a first-time change, and anchor every score in examples from your own plant.