When a GMP project needs Monte Carlo on its program
Two independent long-lead paths, each 80% likely on time, give a 64% chance that both arrive for qualification. A qualitative FMEA register manages risks one at a time; a Monte Carlo schedule analysis adds them up and gives P50 and P80 dates. It earns its cost where paths converge on a fixed date.