"Compression room at no more than 45% RH" in a batch record is a line the receiving site's room has to hold through the wet season too.
Whether it can is a gap analysis question, and the cheap moment to ask it is before the transfer is agreed. WHO's technology transfer guideline (TRS 1044, Annex 4, 2022) says the first steps should include due diligence and a gap analysis through visits to both sites, and that the receiving unit's utilities, HVAC, gas and water among them, should have sufficient capacity.
The facility part of that analysis, line by line:
- Room grade and pressure cascade for every process step, against where the product is made today.
- Containment: the product's exposure limit against what the rooms, dust extraction and return-air filtration were designed for.
- Temperature and humidity the rooms have held in their worst month, from trend data. The design specification is not evidence of that.
- Utilities: water grade and capacity, compressed air and gases at the quality the process needs, HVAC capacity with the new loads.
- Equipment: working principle and scale, side by side with the sending site.
Each line ends as "meets", "gap, with an action" or "gap accepted, with a reason". The guideline also says the impact of the incoming product on products already made on site, and the reverse, should be assessed.