Before a GMP inspection, the inspector has usually read your Site Master File. One section of it belongs to engineering.

The EU Explanatory Notes on the preparation of a Site Master File say that, when submitted to an authority, the file should provide clear information that is useful in planning and undertaking inspections. Section 4 of the content list is Premises and Equipment. Check these entries against the drawings in force today:

  1. The layouts in Appendix 6 show the room classification and the pressure differentials between adjoining areas.
  2. The HVAC description gives the principles for defining air supply, temperature, humidity, pressure differentials and air change rates, and the policy on air recirculation (%).
  3. The water section gives the quality references of the water produced, with schematic drawings in Appendix 7.
  4. Other relevant utilities, such as steam, compressed air and nitrogen, each have a brief description.
  5. Appendix 8 lists the major production and laboratory equipment, with the critical pieces identified.

The Notes prefer simple plans and schematic layouts to narrative, and they let each appendix carry its own effective date. That matters after a project. The pressure cascade drawing moves to a new revision, Appendix 6 stays where it was, and an inspector who arrives with the old layout finds the difference at the first door.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Industries

Related

More on this subject

The first 90 days of a GMP maintenance takeover

Taking over HVAC maintenance in a running GMP plant starts with four outputs in the first 90 days: a walk-down of every asset behind a GMP parameter, a criticality ranking, the calibration status of every BMS and EMS input, and ownership of open HVAC deviations and CAPAs.

InsightRead