Night setback in a Grade C room shows up on the electricity meter within a month, and in the change control log the same week.
Reducing airflow when a room is empty, resetting a supply temperature, widening a humidity band: each changes a condition the room was qualified at. Under EU GMP Annex 15 the change goes through change control, and the risk assessment decides how much has to be requalified.
For a cleanroom that list can get long. Classification counts under ISO 14644-1:2015 scale with floor area: a 50 m² room needs 10 sample locations, and a Grade C room is classified at rest and again in operation. Then come recovery tests, pressure cascade checks, an update to the contamination control strategy and a slot in the QA review queue. Room downtime is the cost most easily left out of the spreadsheet.
A proposal that prices this next to the kWh gets a faster answer from QA, and a more honest payback period.
The cheaper route is to design the reduced mode in from the start and qualify it once, with its own recovery data. Humiley does its energy modeling during design, targeting a 30% reduction in HVAC energy, and design is also the stage where a setback mode can still be qualified with the rest of the system.
Topics
Industries