On a 22/0.4 kV Dyn11 transformer the 3rd harmonic mostly stays inside the building. The 5th and 7th from a fan wall do not.
The reason is sequence. In a balanced system the triplen harmonics (3rd, 9th, 15th) are in phase on all three phases. On the LV star side they add up in the neutral. On the delta primary they circulate round the winding as a loop current and do not appear in the 22 kV line currents.
They are not harmless for that. The circulating current heats the transformer, and the LV neutral carries the sum, which is why neutral sizing and transformer derating come up wherever there is a lot of single-phase electronics.
EC fan walls are different. Their six-pulse rectifiers produce the 5th, 7th, 11th and 13th. Those are not zero-sequence, so the delta does not trap them. They pass through, shifted in phase, and show up on the MV side where the utility measures.
Two practical points. A study that only looks at the MV meter will not see the triplens heating your transformer. And the fan-wall harmonics are the ones that count at the point of common coupling, so treat them at the source. With DC chokes, EC fan THDi is typically 35 to 42%; without, 65 to 75%. We size active filtering from a harmonic study, targeting THDi ≤ 5% at the PCC.
Unbalanced loads let some triplen current through, so measure rather than assume. Questions to an engineer: contact@humiley.com.