"Decide on filtering from a harmonic study" is one line in a specification. The study behind it has five parts.

We write that line ourselves, so this is what we expect the study to contain.

  1. Collect the single-line diagram, the transformer data and the short-circuit level at the point of common coupling (PCC). IEEE 519-2022 sets its current limits as total demand distortion (TDD), and the limit depends on the ratio of short-circuit current to maximum demand load current. Without the fault level there is nothing to compare with.
  2. List the non-linear loads: drives, EC fans, UPS, rectifiers. Ask each vendor for the harmonic current spectrum with the choke actually fitted. A 6-pulse EC fan sits around 35–42% THDi with a DC choke and 65–75% without.
  3. Measure the existing distortion where the site is live. Background voltage distortion from the grid and the neighbours is there before the new load is.
  4. Model the network and compare the result at the PCC with the voltage distortion and TDD limits, for the load cases that will occur. Include generator supply: a generator has a far lower fault level than the grid, so the same currents distort its voltage more.
  5. Select the mitigation, install it, then measure again and keep the report.

Step 5 is the one most often dropped, and it is the only one that shows the model was right.

Our own design target is THDi ≤ 5% at the PCC. In Viet Nam, Circular 05/2025/TT-BCT applies as well.