Eight EC fans on one 30 mA RCD can trip it with no fault anywhere, from the leakage current each fan's EMC filter sends to earth.
Every EC fan carries a small drive whose EMC filter has capacitors from the lines to earth, passing a continuous current in normal running. One fan's worth is small. A fan wall adds them up, because the fans share a circuit and run together.
Worked example: suppose the datasheet gives 3.5 mA per fan. Eight fans put 28 mA on the protective conductor before anything has gone wrong. An RCD rated 30 mA may trip at anything from half its rating, 15 mA. Switching the wall on, or a voltage dip that restarts every drive at once, can be enough.
The first remedy is arithmetic. Split the wall so each RCD carries well under half its rated residual current, or confirm that the installation rules let that circuit run without one. Four of these fans on one device already make 14 mA.
The device type matters as much as the count. Three-phase EC drives can produce smooth DC residual current, which an ordinary type A RCD may not detect, so use the type the fan maker specifies.
And the earth carries that current all the time. Above a threshold the IEC rules ask for a reinforced or duplicated protective conductor, and a loose earth on a leaking fan puts the current on the casing.