The L1 on an AHU datasheet was most likely measured on a box the manufacturer built once, to the dimensions EN 1886 sets for the test.
The model box makes an L1 or TB2 comparable across catalogues, but says little about the unit on your delivery note.
Your unit has its own panel sizes, more doors, access hatches for each filter section, pipe and cable penetrations for coils and sensors, and perhaps a transport split joined on site. Air leaks and heat bridges at joints, and most of those joints were never on the model box.
FAT is the first chance to look at them on the real thing. With the unit assembled in the factory you can inspect door seals and hinges, penetration sealing, panel joint finish and the filter frame gaskets, and run a casing leakage test on the actual unit if the specification calls for one.
Give the filter frames extra time. EN 1886 classes the bypass leakage around a filter frame, with F9 the tightest class. Air that slips round a fine-filter frame carries its dust downstream, so the terminal HEPA filters load faster and reach their final pressure drop sooner. At FAT that is a gasket and a re-check.
Every Humiley unit is FAT-tested and witnessed, and the results go into the equipment file so IQ starts from a complete record.