EN 1886 casing: five classes on one datasheet

  • Manufacturing & Distribution
  • 1 min read

On a draw-through AHU, the casing between the final filter and the fan runs below plant-room pressure.

A leak in that section pulls unfiltered plant-room air in after the filter. A loose gasket at the filter frame does something similar: air slips round the media, and the filter's own efficiency class does not account for it. EN 1886 gives each of these a class, air leakage (L1–L3) and filter bypass (up to F9), and sets three more beside them: mechanical strength (D1–D3), thermal transmittance (T1–T5) and thermal bridging (TB1–TB5). Each class rests on a defined test, so two offers that list all five can be compared line by line.

Thermal bridging is the class offers most often leave blank, and in a humid plant room it decides whether water forms on the casing. Where the frame crosses the insulation, the outer skin runs colder than the panel face. Once that spot is below the plant-room dew point, condensate forms on it, runs down the panel and collects under the unit.

A witnessed FAT checks only part of this list. Transmittance and bridging classes come from a model box tested in a laboratory, and nothing done to a delivered unit measures them again, so the model box test report belongs with the offer. Casing leakage can be tested on the real unit, and the FAT is also the moment to look at panel joints and the filter frame seal.

AeroSano hygienic air handling units

Industries

Related

More on this subject

One differential gauge per filter stage

A single differential gauge across several AHU filter stages cannot say which stage loaded, so teams change everything or guess. A gauge per stage, marked with the commissioning reading and change limit and kept on the calibration list, allows each stage to be changed on condition. BMS transmitters add a trend.

InsightRead