Air at −60 °C dew point holds about 0.007 g of water per kilogram.
Outdoor air in southern Viet Nam holds around 20 g/kg, roughly 3,000 times more.
That ratio is why the envelope sets the load in a battery dry room. Every gram that gets back in has to be picked up by the supply air, and air that dry can take very little. A rough sum: 1 m³/h of outdoor air leaking in brings about 23 g of water per hour. If the supply leaves the dryer at −70 °C dew point, 10 K below the room, each kilogram of it can absorb only about 0.005 g. That single leak uses up around 4,000 m³/h of supply air.
The sources are ordinary ones: operators breathing and sweating, a door held open for a trolley, a cable penetration sealed with the wrong compound, moisture diffusing through panel joints and some floor coatings, materials brought in from a humid corridor.
So the envelope belongs in the equipment specification. Airlock design and door interlocks, vapour tightness of panels and joints, sealed penetrations, the number of people and their garments, and room pressure all go into the moisture load calculation next to the dryer selection. Leave them out and the unit looks oversized on paper and still misses the dew point in production.
We design Li-ion dry rooms to −60 °C dew point and below.