Grade B change rooms: one room or two

  • Life Sciences
  • 1 min read

Annex 1 calls separate change rooms for entering and leaving Grade B "desirable". On a tight footprint that word gets read as "optional".

Two lines in the 2022 revision frame the decision. Separate changing rooms for entry and exit of Grade B areas are desirable. And the final stage of a changing room should, at rest, be the same grade as the area it leads into.

With one change room, operators coming out in used gowns pass through the same space as operators gowning in. Separation is by procedure and timing: benches, floor markings, who goes when. It saves a room and keeps the pressure cascade simple, one step between the corridor and Grade B. It also puts your contamination control on the discipline of the busiest shift change of the day.

With separate rooms, flow runs one way. Gowning in steps up through the grades into B; the exit route never crosses it. The cost is real: more doors to interlock, more airlocks to hold at their pressure step, more supply air, more area to qualify and clean. Grade B still has to stay positive to the exit room, typically by 10–15 Pa per step.

On a new build we would draw the two-room layout first and take it out only with a written risk assessment that sits in the Contamination Control Strategy. On a retrofit the answer is often one room, and then the procedure has to carry what the walls do not.

Industries

Related

More on this subject

EU GMP Annex 1 (2022) gives WFI circulation above 70 °C as an example of minimizing the risk of microbial growth. Keeping a loop hot drives the design: ASME BPE dead legs of L/D ≤ 2, turbulent flow to the last user point, planned sanitization and sensors on the return. The CCS should justify all of it.