Mill scale from new chilled-water pipe ends up in two places: the seat of a control valve and the tubes of a cooling coil.
Black steel arrives with scale on the bore, and installation adds weld slag, swarf and jointing compound. Start the pumps and the water carries all of it to the narrowest passages in the loop. A valve that cannot seat passes water at zero demand. A coil with debris in its tubes loses flow and corrodes under the deposit.
The cleaning sequence that prevents this is short, and the order matters:
- Bypass every coil and control valve, and the chiller evaporators. Fit temporary strainers.
- Flush the mains at the velocity the cleaning guide gives for each pipe size, until the strainers stay clean.
- Circulate the cleaning chemical, then rinse until the water meets the limits agreed with the water treatment specialist.
- Dose inhibitor and biocide straight after the rinse.
- Open the coils, flush through them, clean the strainers again and record the water analysis.
After that the water has to keep moving. A treated system left stagnant for weeks before handover can grow bacteria and need cleaning again.
The drawings have to allow for it: flushing bypasses at the coils, drain points at the low spots, a pump that can reach flushing velocity. Whichever guide the project names (in the UK usually BSRIA BG 29), its acceptance limits belong in the specification before the pipe is ordered.