ISO 14644-3 is a menu of tests, and someone has to order

  • News
  • 1 min read

A specification that says "test to ISO 14644-3" has named a menu of eleven tests and ordered none of them.

Part 3 of ISO 14644 lists supporting tests and gives a method for each. Classification by particle concentration is not among them. That is ISO 14644-1, which Part 3 says shall be carried out to classify a room. Everything else is a supporting test: air pressure difference, airflow, airflow direction and visualization, recovery, temperature, humidity, installed filter system leakage, containment leak, electrostatic and ion generator, particle deposition, and segregation.

The 2019 edition is plain about their status. The tests may not all be required for any given project, and tests and methods should be selected in a manner agreed between the customer and the supplier.

That agreement is where test scopes go wrong. The contractor prices the shortest reading of that line in the specification, and the argument starts at handover, when QA asks for a recovery test nobody planned.

Part 3 supplies the methods. The list of tests, the occupancy state for each and the acceptance criterion have to be written into the test specification before a contractor prices it.

Related

More on this subject

ISO 13485 §6.4.2 asks for documented contamination control without naming a cleanroom class. Setting the class from sterilisation method, patient contact and bioburden sensitivity often lands device assembly at ISO 8, with ISO 7 only where needed, less air than Grade C, a smaller AHU and a reason an auditor can read.

InsightRead

Energy savings and the requalification bill

Energy measures that change validated cleanroom conditions go through Annex 15 change control. Classification alone can mean 10 sample locations for a 50 m² room, at rest and in operation, before recovery tests and a CCS update. Price that next to the kWh, or design reduced modes in and qualify them once.

InsightRead