A pressure tap in the throw of a 3 m/s supply jet can read up to about 5 Pa wrong on a freshly calibrated transmitter.
The bound is velocity pressure, ½ρv². With air at 1.2 kg/m³, 3 m/s gives 5.4 Pa and 1 m/s gives 0.6 Pa. Which way the error goes depends on the geometry: air grazing across the opening tends to pull the reading down, air aimed into it pushes it up. Annex 1 guidance puts adjacent grades at least 10 Pa apart and many rooms are designed at 10–15 Pa, so an error of this size is a third to half of the signal, and it changes every time a damper is rebalanced.
What to check on a room that drifts:
- The tap sits out of the throw of supply diffusers and clear of the door swing. A tap beside a door records every opening.
- Tubing runs without kinks, flattened bends or low loops. Condensate that settles in a low point offsets the reading by the height of the water.
- Both tube runs to a differential transmitter are of similar length, so a door event reaches both ports at about the same time.
- The reference port sits in still air. A reference in a busy corridor or open to outdoors adds wind and traffic to every room measured against it.
A calibration certificate covers the transmitter on the bench and says nothing about items 1 to 4.