Set diffuser one to its design flow, move on to diffuser two, and diffuser one has changed.
Terminals on a branch share one duct pressure. Close a damper and the pressure rises, so the others take more air. Chasing design figures one terminal at a time goes round the room without settling.
Proportional balancing uses a different fact. While the dampers downstream of a point are left alone, the terminals keep the same share of whatever air arrives. So the shares are set first and the total last.
- Confirm the system is complete: ductwork sealed, fire and volume dampers open, clean filters in, fan running near its design total.
- Measure every terminal with the same hood and divide measured flow by design flow.
- Find the terminal with the lowest ratio and leave its damper fully open. Working back toward the fan, throttle each other terminal until its ratio matches. Read the open terminal again each time, because its ratio climbs as the others close. Then balance branch against branch the same way.
- Reset the fan speed so the total reaches design. Every terminal arrives together.
- Lock each damper, mark its position and record the flows, the fan speed and the instrument used.
A balanced system has one fully open damper on every branch. If every damper is half shut, the fan is working against resistance that the balancing added.
Tolerances come from the commissioning code the project names.