The QC lab is often drawn like an office with benches, on a separate HVAC system and off the cascade drawing.
Then look at what goes on inside it. Samples arrive from Grade C and D production through a pass box. The microbiology lab handles open cultures and runs sterility tests. The chemistry lab has fume hoods, and every time a sash goes up the exhaust changes the room balance.
Each of those is an air-direction decision.
Which way should air move between the sampling corridor and the micro lab, and between the micro lab and the rest of QC? A fume hood running at full exhaust can pull a chemistry lab strongly negative. That is fine for the lab. It is less fine if the air it pulls in comes from a corridor shared with production.
Annex 1 puts the Contamination Control Strategy at the centre. A CCS that covers the filling suite in detail and says nothing about where samples go afterwards has a gap the inspector can find by walking the sample route. Where rooms are graded, the same numbers apply: Annex 1 guidance of at least 10 Pa between adjacent grades, typically designed at 10–15 Pa.
Our approach is to put the labs on the same cascade drawing as production, with the sample route marked, before the lab HVAC is sized.