Annex 1 asks for at least 3 consecutive successful aseptic process simulations, covering all working shifts, to validate a new process.
On a three-shift line that means the night crew too, not only the day shift. Periodic runs follow, normally twice a year per process, line and shift.
Each run assumes the cleanroom is in the state it was qualified in: the airflows and pressure cascade from OQ, the same setpoints, the same HEPA filters. That state has to hold from the first fill to the last, through the weeks of incubation in between. A run with contaminated units breaks the consecutive series and opens an investigation, and an HVAC change made mid-campaign is the first thing that investigation will ask about.
The practical answer is an HVAC freeze date agreed with QA before the first fill. By then the balancing reports are signed and the BMS setpoints locked, with spares on the shelf for any part that would stop a unit. It also pays to list in advance which jobs count as like-for-like maintenance during the campaign, such as a pre-filter change or a calibrated sensor swap, and which need an impact assessment against it: a new fan, a changed setpoint, a replaced terminal HEPA that needs a leak test.
Our qualification roadmap is written alongside the design, so the date the HVAC must be stable is on the program from the start.
Which HVAC jobs does your change control treat as like-for-like during an APS campaign?