EU GDP expects a store to be temperature-mapped before use. Plenty of warehouses do it after the racks are full.
Map an empty store and a hot spot is a design finding: move the probe, add a diffuser, mark the top two rack levels near the roof as no-go for 15–25 °C product, and write it into the layout. Map a full store and the same hot spot is a deviation. Now someone has to work out which pallets sat in that position, for how long, through which weeks, and where they went.
In Viet Nam the hot spots are predictable: the underside of a metal roof in the dry season, the rack face beside the dock doors, the corner the supply air never reaches. Mapping proves where they are before product is exposed.
The guideline asks for representative conditions, and that is the part to argue about early. Racking installed, HVAC in its normal mode including any night setback, doors operated the way the site will use them, and a plan for the seasonal repeat, because a store mapped in December has not seen April.
GDP also expects the mapping to be repeated according to a risk assessment, or whenever there is a significant change to the store or its temperature control. New racking height counts.
On our projects the qualification roadmap, mapping included, is written in parallel with the design, so the probe plan and the HVAC layout are drawn by people talking to each other.