When a signal cable screen is earthed at both ends

  • News
  • 1 min read

Room pressure on the trend wanders by a pascal or two whenever the exhaust fan drive ramps, and the door has not moved.

The transmitter is usually fine. Look at the screen of its signal cable. If it is bonded to the transmitter housing and again to the earth bar in the panel, it joins two earth points that are never at quite the same potential. The difference pushes a current along the screen, and the signal pair picks part of it up. On a 4–20 mA transmitter ranged 0 to 100 Pa, one pascal is 0.16 mA.

The usual rule for analogue signals, and the one in most transmitter manuals: bond the screen at one end, normally the panel, and cut back, sleeve and insulate the other.

Two more faults give the same symptom. At junction boxes the screens are cut back and never joined, so the cable beyond the box has no screen. Or the bare drain wire at the field end touches the gland, a second earth that is on no drawing.

Bonding at one end is a low-frequency rule: IEC/TR 61000-5-2 prefers screens bonded at both ends where the bonding network holds both ends at the same potential, and drive motor cables are bonded at both ends. Bus cables follow the bus maker's rule; for RS-485 buses such as Modbus RTU and BACnet MS/TP that is often one point. State the rule per cable type in the installation specification.

As a quick test, lift the screen at the panel and measure it to earth. The correct reading is open circuit.