Raising chilled water by 2 K saved chiller energy in March. In July the rooms drifted wet, and nobody connected the two.
The logic was textbook. When every cooling valve is partly closed, the plant is making colder water than the coils ask for, so the BMS resets the supply temperature upward, from 7 °C to 9 °C in this example, until the most open valve is nearly open. The chiller lifts less.
What valve position cannot tell the BMS is why a coil wants cold water. A coil that only cools is satisfied by a warmer supply. A coil that has to dry the air needs its surface below the dew point it is asked to deliver, and a room held at 22 °C and 50% RH has a dew point near 11 °C. With water 2 K warmer the coil surface sits too close to that. The valve goes fully open, the supply air temperature is still met, and the moisture stays in the air.
The reset had been commissioned in the dry season, when the outdoor dew point was low and the latent load small. It passed.
Three changes fix it. Lock the reset out on outdoor or supply-air dew point, so it acts only when there is little to dry. Test the sequence again on a wet-season day, with room humidity on the trend. And list which coils dehumidify before any reset is written, because those coils set the water temperature for the plant.