Annex 15 allows some FAT tests to count at IQ and OQ, if transport and installation did not affect what they proved.
The wording in section 3 is cautious. Where appropriate and justified, documentation review and some tests done at the FAT need not be repeated on site. The burden sits with whoever relies on the factory result.
For an AHU the useful document is a short list of what the trip to site can change. Fan and motor alignment can shift on a truck. Casing leakage changes when sections are split for transport and rejoined. Sensors drift, the field wiring is new, and the control software on site may not be the version that ran in the factory. Those get tested again after installation. Material certificates, component checks and software functions that do not depend on site I/O are the candidates for referencing.
Two habits make that referencing easier to defend, although the Annex does not require either. Have the FAT protocol approved before the test by the same QA function that will approve IQ and OQ. And record deviations at the FAT and close them there, so a repair made on the shop floor has paperwork behind it.
A thinner site OQ is paid for with a longer, better documented FAT. Whether that trade suits a project depends on where the factory is and who can travel to witness.
Every unit we supply is FAT-tested and witnessed, and the equipment file is compiled during production.