High room humidity: five checks, in order

  • News
  • 1 min read

When a room reads 65% RH against a 60% limit, the usual first move is more reheat. On our list that check comes fourth.

Reheat brings the RH number down by warming the air. The water is still there and the energy bill has gone up. So before touching it, work from outside the building inwards.

  1. Outdoor dew point against the design value. If today is wetter than the design day, the coil is being asked for more than it was sized for.
  2. Chilled water supply temperature and the cooling valve position. A valve at 100% with water arriving 2 °C warm is a chiller plant problem that shows up as a humidity alarm.
  3. Coil leaving dew point. This is the reading that says whether water is being removed. If it is above the room's target dew point, nothing downstream will dry the room.
  4. Reheat, and the room sensor checked against a reference instrument. Sometimes the room is fine and the probe has drifted.
  5. Doors, infiltration and new moisture sources: a door propped open to a wet corridor, or a wash-down moved to the day shift.

Each of the five is one BMS trend. Pulling all five for the same hours takes less time than the meeting about whose fault it is.

The order is a habit and it has exceptions. If the alarm began in the minute a shift started, begin at 5.

In a tropical climate we size the fresh-air coil on peak dew point, which is why check 1 comes first.

Which of the five can your BMS not show?