Every socket box in a cleanroom wall is part of the pressure calculation, whether the designer counted it or not.
A room holds its differential because more air is supplied than extracted, and the excess leaves through whatever gaps exist. The orifice equation links the two. For the same excess airflow, the pressure difference goes with the inverse square of the leakage area. Double the leakage area and the differential falls to a quarter.
On a finished room that area hides in ordinary places. The gap under a door and around its frame, usually the largest single path. Recessed light fittings not gasketed to the ceiling grid. Sockets and switches with open back boxes into the wall void. Panel joints where sealant was skipped behind a riser. Penetrations for sprinkler drops, sensors and cable trays.
Designers estimate leakage early, often from door gaps alone. Then the room gets built and every trade adds a few square centimetres of its own.
The check at commissioning is simple. Measure the excess air it takes to hold the design differential and compare it with the design allowance. If it is well above, walk the room with a smoke pen before anyone touches the balancing dampers.
Where does your team usually find the leak the drawing did not show?