A board corrected to 0.98 displacement power factor can still read about 0.91 true power factor. Harmonics make up the gap.
Power factor has two parts, and capacitors fix one of them. Displacement power factor is the cosine of the angle between fundamental voltage and current. Motors and transformers push it down; capacitors pull it back.
Distortion is the other part. Drives, EC fans and rectifiers draw current in pulses, and the harmonic content adds apparent power that does no work. With undistorted voltage, true PF = DPF × 1/√(1 + THDi²). At 40% THDi, 1/√1.16 ≈ 0.93. A board with DPF corrected to 0.98 and 40% THDi reads about 0.91 true PF, and extra capacitance will not move it.
40% is not exotic. A 6-pulse drive with a DC choke typically draws 35–42% THDi, as does an EC fan wall with DC chokes; without chokes it is nearer 65–75%.
Chasing the gap with more capacitors makes things worse. Harmonic current flows into them, they heat up, and the bank can resonate with the transformer at one of the harmonic orders. The fix is on the distortion side: DC chokes, active harmonic filters sized from a study, and the IEEE 519-2022 TDD limit for the site's short-circuit ratio as the target at the point of common coupling.
When you commission a power-quality study, ask for the two factors to be reported separately. Then you can see which one the tariff charges for.
Which power factor does your utility meter measure?