Seven degrees of apparatus dew point on a coil schedule does not mean 7 °C dew point air in the duct.
The apparatus dew point (ADP) is the effective coil surface temperature, the point where the coil condition line meets the saturation curve. Air leaving the coil sits on the straight line between the entering state and the ADP, and stops short of it by the bypass factor (BF). Leaving = ADP + BF × (entering − ADP), for dry bulb and for moisture content alike.
A worked example with BF 0.1, so 10% of the air behaves as if it missed the fins. Mixed air enters at 26 °C and 12 g/kg. The ADP is 7 °C, where saturated air holds about 6.2 g/kg. The air leaves at about 8.9 °C and 6.8 g/kg, a dew point near 8.3 °C. More than 1 K of drying never happened.
In a comfort system nobody notices. In a room with a tight humidity limit on a wet afternoon, that gap is the humidity excursion.
So work backwards. Start from the dew point the supply air needs, allow for the bypass, and find the ADP the coil must reach. For 7 °C dew point leaving air in this example, the ADP has to sit near 5.4 °C. That number sets the chilled water temperature and the row count.
Our AHU selection platform runs these psychrometrics before a coil is chosen.
Which bypass factor do your coil vendors quote, and is it on the data sheet?