Drying 10,000 m³/h of wet-season air pulls about 170 kg of water out of it every hour. Most plants pipe it to the drain.
The arithmetic is short. 10,000 m³/h of outdoor air is about 12,000 kg/h. At a 26 °C dew point it carries roughly 21.4 g of water per kg of dry air. Cooled to a 9 °C dew point for a GMP space, it leaves at about 7.1 g/kg. The difference, around 14 g/kg, times 12,000 kg/h is roughly 170 kg an hour. Held at full load for a day, that is about 4 m³.
This is a worked example, not a measured plant. Real volumes follow the weather and the load, and the wettest afternoons produce the most.
The water is condensed vapour, so it is low in dissolved minerals. That makes it a candidate for cooling tower make-up, or a feed that needs less softening than raw water. It has also been sitting in a drain pan on a coil, so it carries whatever grows there and whatever the air brought in. Reuse needs a site assessment: collection, storage time, treatment, and where it may and may not go.
We size fresh-air coils on peak dew point anyway, so the condensate figure comes out of the same load calculation. It is worth putting on the drawing.