After more than twenty years with automation vendors and running an EU-GMP EPC contractor, Tony Nguyen saw problems start at the handovers between companies rather than inside any one scope. This note explains why Humiley is organized as one accountable team across design, project management, equipment and maintenance.
Where a SCADA, BMS or EMS records GMP-relevant data, access control, clock synchronization, alarm records and audit trails are decided by the electrical and automation engineers. Many sites keep those parameters on a separate validated EMS. Humiley's cross-functional training covers GMP, validation and project management.
Commissioning is good engineering practice owned by engineering; qualification is QA-approved evidence on critical aspects. ISPE Baseline Guide Volume 5 and ASTM E2500 let one test serve both, if it was identified in advance, run to an approved protocol and agreed with QA before it ran.
A drawing package with 400 hours planned, 300 due and 200 earned has an SPI of 0.67; at that pace the remaining work takes about 1.5 times the planned time. Design engineers who check their own line in the monthly report, and log vendor waits on the weekly FMEA register, see slips early.
A failed acceptance criterion and a protocol step not executed as written are different OQ deviations. The first needs root cause, impact assessment, a fix and a repeat test; the second needs an assessment of whether the result still stands. Changing a criterion after a failure invites audit questions.