A drawing package with 400 hours planned, 300 hours' worth due by month end and 200 hours' worth earned has an SPI of 0.67.
Nobody on the team has called the package late yet. The earned value line in the monthly report already shows it: a schedule variance of minus 100 hours, and if the pace holds, the remaining 200 hours of work will need about 1.5 times the time the plan gave them.
A design engineer can get a lot out of that report by finding their own package in it and checking the issue dates against the ones they are really working to. Say the planner has the duct layout issuing on the 12th, and you know the layout waits on coil data the vendor has not sent. Then the report is wrong before anyone reads it.
That vendor wait also belongs on the risk register. Our EPCM projects keep a live FMEA register reviewed weekly, and a line like "coil selection waiting on vendor performance data, needed by the 12th" is a design risk the person drawing the layout usually spots first. Written there with a date, it gives the project manager time to chase the vendor.
Project management is one of the three subjects in our cross-functional training, with GMP and validation, and senior leads mentor on the job.
Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)