The same airflow balance gets tested twice on many projects: once by the commissioning team, again by the qualification team a month later.
The two activities answer different questions. Commissioning is good engineering practice, owned by engineering: does the system work as designed? Qualification is documented evidence, approved by QA, that the aspects critical to product quality and patient safety meet their requirements.
ISPE's Baseline Guide Volume 5 (second edition, 2019) and ASTM E2500 both allow a commissioning test to serve as qualification evidence. The condition is how it was run, not who ran it. To count, the test must be on a critical aspect identified in advance, run to an approved protocol with acceptance criteria, with calibrated instruments, recorded as it happened, and with deviations handled. QA does not have to witness everything, but it has to have agreed that the test would count before it was run.
Miss any of those and the result is good engineering data that QA cannot sign. Then the test is repeated, the schedule slips, and nobody learns anything new from the second run.
In our EPCM work, commissioning and qualification plans are written together, so the critical tests are identified early and run once.
On your last project, how many commissioning tests could QA actually accept?



