Two accountable parties on one RACI row means nobody decides. The rows most likely to collect two As cross a handover: design changes after tender, vendor drawing approval, long-lead releases and readiness for IQ. Read every row as "X decides" and fix the ones that need two names before kickoff.
Most of a cleanroom HVAC contract is paid before the turnover documents exist. Split the retention into two parts, released on acceptance of the turnover package and of the documents, and size the documentation part on what it would cost the owner to finish as-builts, calibrations and retests without the contractor.
Contingency reserve covers risks already on the register, sits inside the cost baseline and is drawn by the project manager against a named risk. Management reserve covers what nobody has listed, sits outside the baseline and is released by the owner through a change. Mixing them empties the pot before the risk arrives.
Contractor method statements are written for safety. For work in a GMP area, review them again for the product: the exact systems touched, the pressures and alarms affected and who is told, contamination control, isolations and permits with the change control number, and the reinstatement tests and signature that release the room.
The critical path is the longest chain of dependent activities from today to the finish, and its activities have no float. Size, cost and importance are not part of the calculation, so a calibration certificate can sit on the path while a major delivery has weeks to spare. The path changes at every schedule update.