Contingency and management reserve are different money

  • Project Management Consultancy
  • 1 min read

One budget line called "contingency" usually hides two different pots of money with two different owners.

Project management practice splits them.

Contingency reserve covers risks already on the register: a long-lead AHU arriving late, rock under the utility trench, a vendor drawing that fails review and costs a second round. Each has a probability and an estimated cost, and the contingency is sized from them. It sits inside the cost baseline. The project manager draws on it when one of those risks happens and records which risk the money went to.

Management reserve covers what nobody has listed. It sits outside the baseline and the owner or sponsor holds it. Drawing on it is a change: the baseline goes up, and the reason is written down.

When the two are mixed, one of two things tends to happen. Contingency gets spent on scope growth because the money was there, and the listed risk arrives to an empty pot. Or the owner treats every draw as a crisis, and the project manager learns to report risks late.

The size of the contingency is informative too. If it does not trace back to the risk register, it is a percentage somebody picked.

In our EPCM work the FMEA risk register is live and reviewed weekly, which is where a contingency figure should come from.

Who holds the reserve on your current project, and does the project manager know how large it is?

Related

More on this subject

Four checks at the basic-design gate

Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.

InsightRead

Two envelopes for a cleanroom HVAC tender

Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.

InsightRead