Two names in the A column of a RACI chart means nobody is accountable for that row.
It usually happens for a decent reason. The owner's engineer and the contractor both care about the AHU selection, so both get an A. Then the selection needs a decision on a Friday afternoon, each side waits for the other, and the vendor's quotation expires over the weekend.
The four letters describe different jobs. R does the work, and there can be several. C is asked before, I is told after. A signs, and answers for the result when it turns out wrong. That one has to be a single person or a single role, or the chart is describing a committee.
On GMP projects the rows that collect two As are the ones that cross a handover: a design basis change after tender, vendor drawing approval, releasing a long-lead item, and the call that a system is ready to leave construction for IQ.
A quick test before kickoff: read each row aloud as "X decides". If it only works as "X and Y decide", fix the row while nobody is yet arguing about a real AHU.
In our EPCM work the RACI sits alongside the weekly FMEA risk review and the monthly report on schedule, cost and earned value.
Run that test on your current chart.