A contractor's method statement, read for GMP impact

  • Project Management Consultancy
  • 1 min read

Replacing the actuator on damper D-12 takes ten minutes. On the return duct of a Grade C room, that is ten minutes without pressure control.

Most contractor method statements are written for safety, which is what they were invented for. Reviewing one for a GMP area means reading it a second time for the product. On that second reading, look for:

  1. The exact place and every system touched: room numbers, the AHU, tag numbers. "Ceiling void, production block" is not a location.
  2. What the work does to the room while it is going on: which pressures and alarms are affected, for how long, who is told beforehand, and who inhibits and restores each alarm.
  3. Contamination control: how drilling and cutting dust is contained, how tools and materials are cleaned at the entry, the gowning for that grade, the route out for waste.
  4. Reinstatement: the tests that show the system is back, such as stroke and position feedback for the actuator and a stable room pressure, then the cleaning, and the signature that releases the room.

The isolations and permits will already be in the document. Check that the change control or work order number is written beside them.

"Like for like" deserves a line of evidence too. A replacement actuator with a different running time gives the pressure loop a different response, even when the label shows the same part family.

Industries

Related

More on this subject

WHO's 2022 sterile GMP and the barrier decision

WHO's 2022 GMP for sterile products (TRS 1044, Annex 2) follows EU Annex 1. For a WHO-prequalification plant the barrier comes first: a RABS needs a Grade B background, a closed isolator Grade D, and that sets the HVAC. The contamination control strategy should be written alongside the design.

InsightRead

A CCS nobody reviews is only a snapshot

Annex 1 expects the Contamination Control Strategy to be actively reviewed and updated. A yearly meeting catches changes late. Adding one question to every HVAC change control, EM adverse trend review and deviation closure form, asking whether the CCS still says the right thing, keeps it current with the site.

InsightRead