Four things belong in the report QA opens after an AHU failure: a timeline, the trend data, the impact on rooms and batches, and a CAPA.
The repair is the engineer's job. The product decision is QA's, and it is made from that document. All four parts can be drafted before the day shift starts.
- Timeline. Alarm time, response time, when the fan stopped, when the rooms were back within limits. Timestamps come from the BMS and EMS, not from memory.
- Data. Trend exports of room differential pressures, temperature, humidity and particle counts for every affected room, with a margin before and after the event, so nobody has to take the engineer's word for what the rooms did.
- Impact. Which rooms left their limits and for how long, whether any pressure reversed between grades, and which batches or open operations were inside at the time. Also what was repaired, and whether it was like-for-like or a change.
- CAPA. The immediate correction, the root cause as far as it is known, and actions with an owner and a date. If the cause needs more work, say so and give the date it will be known.
A report that arrives complete saves QA a day of calls about what happened at the unit.