A 0–1,000 Pa gauge on a pre-filter that is changed at 150 Pa spends its whole life in the bottom 15% of the dial.
Down there one division covers tens of pascals, and a dial quoted at 2% of full scale is uncertain by 20 Pa either way. The filter's working range, from its clean reading to its change point, may be only about 100 Pa wide. The technician is reading a change not much bigger than the needle's error.
Choose each stage's range from its own final pressure drop, so that the change point sits somewhere between the middle and two-thirds of the scale. For the same pre-filter, a 0–250 Pa gauge puts 150 Pa at 60% of the dial, and 2% of full scale becomes 5 Pa.
On one AHU that usually means different ranges. The pre-filter, the bag filter and any HEPA stage each have their own clean and final values, and the HEPA's are the highest. Buying one range for all three because it covers the biggest number leaves the first two hard to read.
Two details follow. A gauge that can see full fan pressure when a damper shuts needs an overpressure rating to match. And transmitters work the same way: scale the 4–20 mA range to the stage, because the BMS trend is only as fine as the range behind it.
Condition monitoring and IIoT trending are part of our maintenance service, and a well-ranged gauge is the cheapest sensor in it.