One differential gauge per filter stage

  • Life Sciences
  • 1 min read

One differential gauge across three filter stages gives you a single number and three filters to replace.

A typical GMP supply AHU carries a pre-filter, an ePM1 bag filter and sometimes a HEPA stage in the unit, before the terminal filters in the room. Each stage starts at its own clean pressure drop and loads at its own rate. The pre-filter sees the dirtiest air and usually loads first.

With one gauge across the lot, the reading climbs and nobody can say which stage did it. Teams then change everything, throwing away filters with life left in them, or change the cheap pre-filter and hope, leaving a loaded bag filter to pull airflow down.

A gauge per stage turns that into a decision per stage. Two habits make the gauges worth having. Mark the clean pressure drop recorded at commissioning and the change limit on each gauge face, so the technician reads against a line rather than memory. Then put the gauges on the calibration list, since they now drive a GMP maintenance decision.

Transmitters into the BMS cost more than dial gauges. They also give a trend, so you can see a stage loading faster than it did last year and go looking for the reason.

Condition monitoring and trending are part of the criticality-based planned maintenance we run for GMP facilities.

On your AHUs, what triggers a filter change today: the calendar or the gauge?

Industries

Related

More on this subject

Clean AHU cooling coils from the leaving face with low-pressure water or steam and an approved, fully rinsed detergent, after checking the drain. Take the frequency from the coil's pressure drop trend against a commissioning baseline, and record the method, detergent batch, before and after readings and photos of both faces.

InsightRead

Plug fan or belt drive in a GMP supply AHU

A V-belt sheds rubber dust into the airstream for its whole life, and in a GMP supply AHU that dust loads the final filters. Belt drives also lose a few per cent of shaft power and need regular tensioning. Direct-drive plug fans avoid all three, though a large belt-driven housed fan can still win at high pressure.

InsightRead

Four maintenance KPIs for a GMP plant

A single PM compliance percentage hides the overdue task QA cares about. Track PM compliance by criticality, overdue critical tasks listed by name, repeat failures on the same asset, and mean time to restore the pressure cascade from the BMS trend. All four need a CMMS asset register with criticality assessed.

InsightRead