A single PM compliance percentage averages the grease point on a roof fan with the leak test on a filling-room HEPA.
That makes it a poor headline number for a GMP maintenance department. It can sit comfortably in the high nineties while the one late task is the one QA cares about. Four measures tell a plant manager more.
- PM compliance split by criticality. GMP-critical assets get their own line. Late tasks on direct-impact equipment are a different conversation from late tasks on the canteen AHU.
- Overdue critical tasks, by name. A list, not a percentage. The target is an empty list, and every entry has an owner and a new date agreed with QA.
- Repeat failures. The same asset failing the same way twice inside a set window, say 90 days. Each one should open a root-cause investigation rather than another work order.
- Mean time to restore the pressure cascade. Taken from the BMS or EMS trend, from the alarm to the last room back inside its limits. It shows how long product was exposed and whether the spares and call-out arrangements work.
All four come straight out of a CMMS whose asset register carries a criticality rating. If criticality was never assessed, start there.