'As per design' is not an acceptance criterion

  • Life Sciences
  • 1 min read

"Room pressure: as per design." On test day the reading is 11 Pa, and the tester has to work out what the design was.

The pressure cascade drawing shows 15 Pa between the room and the corridor, with no tolerance. The URS says at least 10 Pa between adjacent grades. Against one document 11 Pa is a pass. Against the other nobody can say. So the person holding the instrument chooses, and the protocol records "OK".

EU GMP Annex 15 (2015) says validation protocols should be prepared which define the critical systems, attributes and parameters and the associated acceptance criteria. A significant change to an approved protocol during execution, with acceptance criteria among the Annex's examples, should be documented as a deviation and scientifically justified. A criterion settled at the instrument is a criterion changed during execution, with the deviation left out.

A line a tester can apply reads more like this: differential pressure, room to corridor, 15 Pa ± 3 Pa, read on a calibrated micromanometer at the door, doors closed, room at rest, logged for 30 minutes; source, the pressure cascade drawing and the URS, each with its revision.

Against that line the 11 Pa is a fail, and the person holding the instrument has nothing left to choose.