A 50 m² Grade B room is classified twice before release: 10 locations at rest, then the same 10 in operation.
ISO 14644-1:2015 sets the number of sampling locations by floor area, and 50 m² needs 10. EU GMP Annex 1 then requires classification in both occupancy states, ISO 5 at rest and ISO 7 in operation for Grade B, and asks for airflow visualization, the smoke study, at rest and in operation as well. A program that runs either test in one state only does not meet Annex 1.
Where each run sits is left to the site. A common plan puts the at-rest classification and the first smoke study in OQ, once the filters and the main process equipment are installed, the equipment is on standby and nobody is in the room. Before the equipment is in, the room is only as-built. The in-operation runs wait for PQ, when operators, trolleys and machine guards are there to disturb the airflow. Some plans film the in-operation smoke study during simulated operations instead, so a poor pattern turns up before the process simulation. The URS and the risk assessment should say which, and why.
Most other cleanroom tests run once. The installed HEPA leak scan, pressure differentials, airflow and recovery tend to sit in OQ, and some plans pull the leak scan into the end of IQ.
We write the validation strategy and qualification roadmap alongside the design.
Where does your site film the in-operation smoke study?