Dry room make-up air: size dehumidification from the exhaust schedule

  • Renewable Energy
  • 1 min read

Every 1,000 m³/h of outdoor air at 20 g/kg brings about 24 kg of water an hour into a dry room's air handling plant.

The arithmetic is short. At a density of about 1.2 kg/m³, 1,000 m³/h is some 1,200 kg of air an hour, and at 20 g of water per kg that is 24 kg/h. Supply air near −40 °C dew point carries under 0.1 g/kg, so almost all of it has to come out. Outdoor air in Ho Chi Minh City sits near 20 g/kg on many afternoons and above it in the wet season.

The designer does not choose that outdoor airflow freely. It has to replace everything the process exhausts: coating and drying lines, glove boxes, local extraction at slitting and stacking, plus the leakage that keeps the room positive. A line exhausting 5,000 m³/h commits the plant to about 120 kg/h of water before anyone walks in.

So the exhaust schedule comes first. Get flows from the process equipment suppliers early, challenge any exhaust that could be returned instead, and interlock exhaust with make-up air so a machine left extracting cannot pull wet air in through the doors. A cooling coil ahead of the desiccant wheel takes out the bulk of the water on chilled water, and the wheel removes the last grams.

We supply desiccant dehumidification to −60 °C dew point for dry rooms.

Related

More on this subject

Where a desiccant rotor loses its capacity

Desiccant rotors lose capacity slowly: worn sector seals let wet air cross over, a slipping drive slows the rotor, dust and solvent vapour foul the media. Measuring outlet dew point, airflow and reactivation temperature against the commissioning record shows the trend before a −60 °C dry room does.

InsightRead