The dry room that never reaches its dew point usually has a moisture source nobody wrote down.
A low-dew-point room is a mass balance. Water comes in from several places, the desiccant unit takes it out, and the achieved dew point is wherever the two meet. A load calculation that lists makeup air and people and stops there will select a dehumidifier that is right for a room that does not exist.
Makeup air is usually the biggest term, and the psychrometrics show why. Air at a 25 °C dew point holds about 20 g of water per kg of dry air; at a −40 °C dew point it holds about 0.08 g/kg, some 250 times less. Every kilogram of fresh air has to be dried across that gap.
People add roughly 80 g/h each at light work, so two operators and a technician put in 240 g/h while they are inside.
The envelope is subtler. The room is held above its surroundings, so air leaks outward most of the time. Moisture gets in when that pressure is lost: a door held open, both airlock doors cycling close together, a supply fan trip. Count those events per shift. Vapour also permeates panel joints and cable seals whatever the pressure.
Cartons, pallets and electrode rolls release moisture once inside, and wet cleaning adds water directly.
Humiley designs dry rooms to −60 °C dew point and below.
In your plant, which source is hardest to put a number on?