A new dry room loses most of its water quickly on the first pull-down, then the dew point curve flattens above the target.
Air at −40 °C dew point still holds about twelve times the water it holds at −60 °C, so the last 20 K are a contest with whatever keeps giving off moisture: concrete, panel joints, cable insulation, cartons, a leak. The order of work decides whether you can tell which.
- Seal the envelope and leak-check it before the dehumidifier runs: penetrations, door seals, panel joints, and the return ductwork, which sits at negative pressure and draws in whatever is outside it.
- Run the dehumidifier with the room empty. No people, no pallets, no cartons.
- Log dew point against time at the supply and at the return, and plot both.
- Read the flat part. If the supply is at its design dew point and the return sits well above it, water is entering the room: a level line points to a leak, one that keeps creeping down to a material drying out. If the supply itself is high, look at the dehumidifier before the room.
- Bring in people and door openings only after the empty room holds its target, as separate tests.
Moving process equipment in while the curve is still falling saves time on the program, and after that nobody can say whose water it is.
Industries


