What an AHU logbook should hold under EU GMP Chapter 4

  • Life Sciences
  • 1 min read

EU GMP Chapter 4 asks for logbooks on major or critical equipment. Many AHU logbooks we open hold filter change dates and little else.

Logbooks are kept for major or critical production equipment and for areas where product is processed, and they record in time order the use, calibrations, maintenance, cleaning and repairs, with dates and the identity of the people who did the work. An AHU serving Grade B or C rooms is critical equipment under almost any risk assessment. Its logbook should read like it.

Entries we expect in an AHU logbook:

  1. Qualification and requalification events, with report references.
  2. Calibration of the sensors that feed GMP data: room pressure, temperature, humidity, airflow.
  3. Planned maintenance against the task list, including filter changes with the differential pressure before and after.
  4. Breakdowns and repairs, with the change control or deviation number when one was raised.
  5. Cleaning and disinfection of the unit where the procedure calls for it.

Every entry carries a date, what was done and who did it. If a CMMS holds the detail, the logbook can point to it, but an inspector should be able to pull the history of one unit in one sitting.

Our Maintenance Service builds the plan from the project's asset register, so the logbook starts on the day of handover.

Maintenance Service and the other three divisions

Industries

Related

More on this subject

The 2013 text of EU GMP Chapter 1 lists the qualification status of relevant equipment and utilities among the items a product quality review should include. Engineering can make that line believable with four more inputs: changes in the period, excursions and trends, calibration and maintenance failures with product impact, and the status of engineering CAPAs.

InsightRead

45% or 30% RH: what the dew point decides

At 20 °C, 45% RH is about a 7.7 °C dew point, within reach of a cooling coil on roughly 5 °C chilled water; 30% RH is about 1.9 °C and points to desiccant dehumidification. EU GMP gives no RH value, so derive the limit from product moisture data and exposure time before sizing plant.

InsightRead

A month-end note from Tony Nguyen, CEO

After more than twenty years with automation vendors and running an EU-GMP EPC contractor, Tony Nguyen saw problems start at the handovers between companies rather than inside any one scope. This note explains why Humiley is organized as one accountable team across design, project management, equipment and maintenance.

InsightRead