Five checks on a single-line diagram

  • News
  • 1 min read

Months before anyone energises it, a 36 kA breaker on a busbar that can see 38 kA is already drawn on the single-line diagram.

That drawing is where a mechanical engineer can catch an electrical problem early, because the things that go wrong are printed on it. Read it in the direction the power flows:

  1. A fault level in kA is written at each board. For scale, a 1,600 kVA, 400 V transformer at 6% impedance puts about 38 kA on the main busbar.
  2. Each breaker's breaking capacity (Icu, IEC 60947-2) and each board's short-time withstand (Icw, IEC 61439) is at or above the fault level at that board.
  3. Essential loads sit on their own section, with the generator and transfer switch drawn. If the AHUs that hold the pressure cascade share a busbar with the office chillers, load shedding has nothing clean to cut.
  4. Harmonic loads are marked: variable speed drives and EC fan walls, with any filter shown at the board it serves.
  5. The earthing system is stated, and metering is shown where energy will be reported.

The short-circuit and discrimination study still does the proving. A diagram that fails the first two checks usually means the study has not been done yet.

Mechanical changes are often what dates the diagram: a larger chiller, EC fan walls in place of one fan, a second AHU moved to the generator-backed board. Send them to the electrical engineer when they happen.

Related

More on this subject

Four checks at the basic-design gate

Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.