Over one filter cycle, the pressure an AHU fan works against can rise by 200 Pa while the airflow is not allowed to move.
A worked example: the filter bank adds 250 Pa clean and 450 Pa at change-out. Airflow has to hold the whole time, because the room classification and the pressure cascade are built on it.
A fan picked at the 450 Pa point spends most of the cycle slowed down by its drive, holding design airflow against less resistance than it was chosen for. On the reduced-speed curve that puts the operating point right of peak efficiency, at high flow for that speed.
The opposite problem appears when the selection point is 250 Pa and the motor and drive leave no speed above it. That fan runs near peak for a few weeks, then cannot hold design airflow as the filters load, and the cascade downstream drops with it. Give the same fan a VFD and a motor sized for overspeed and it may still reach 450 Pa; then the only question is where it runs efficiently.
In this example we would select near 350 Pa of filter loss, then check design airflow and motor load at 450 Pa with the drive at full speed.
The energy difference between these choices is smaller than the argument suggests: 200 Pa is only part of total pressure beside coils, ductwork and terminal HEPA filters. Loading is rarely linear either, so take the final figure from the filter data.